Phase One (closure of road to south of church) Monday 27th June 2016 to Sunday 24th July 2016 Traffic approaching Load Street westbound will proceed over the bridge on the B4190 Kidderminster Road, on the west side of the bridge (Load Street) will turn immediately left on to Severnside South, right on to Lax Lane, then right on to High Street to access Bewdley town centre.

Traffic southbound from Park Lane/Dog Lane/Wyre Hill will flow along Load Street, right on to Severnside South, right on to Lax Lane then left on to

B4190 Red Hill.

Traffic eastbound will flow as normal during this phase of the works.

 

Phase Two (closure of road to north of church) Monday 25th July 2016 to Friday 16th September 2016 Traffic approaching Load Street westbound will proceed over the bridge on the B4190 Kidderminster Road, on the west side of the bridge (Load Street) will turn immediately left on to Severnside South, right on to Lax Lane, then either right on to High Street to access Bewdley town centre or left on to B4190 Red Hill to head South towards Stourport/Astley Cross.

Traffic eastbound will be diverted around the south side of the church.

This reverses the direction of this one way stretch of road.

 

Both Phases

All heavy traffic would be diverted via the bypass using signage only.

Lax Lane will be one way (south-west bound traffic only).

B4190 High Street will become one way (north-west bound traffic only) during the works.